Project Location: Kyiv, Ukraine
System Power: 500 kW
Energy Capacity: 1 MWh
Application: Off-Grid Resort Microgrid
System Configuration: Battery Energy Storage + Solar PV + Diesel Generators

Project Overview

Enerlution has delivered a 500 kW / 1 MWh containerized Battery Energy Storage System (BESS) for a resort located near the Dnipro River in Kyiv, Ukraine.

The project integrates battery energy storage with 360 rooftop solar panels and two diesel generators, forming a fully off-grid microgrid designed to support the resort's electricity needs.

As an independent energy system without a connection to the public grid, the resort requires a reliable and flexible power supply to support its daily operations, including catering facilities, refrigeration, lighting and other electrical loads.

This project demonstrates Enerlution's practical experience in delivering integrated energy storage solutions for off-grid applications.

500 kW / 1 MWh BESS Project in Kyiv, Ukraine | Enerlution 1

The Energy Challenge: Meeting Changing Electricity Demands

Before the energy storage system was introduced, the resort relied entirely on diesel generators for its electricity supply.

Its electricity demand varied throughout the day. During meal preparation periods, multiple high-power commercial induction cookers and other electrical equipment could operate simultaneously, resulting in significant peak power demand.

At night, electricity consumption decreased, but the diesel generators still needed to operate to supply the resort.

This createdThe project therefore required an integrated energy solution capable of coordinating solar generation, battery storage and diesel power generation to better match electricity supply with actual demand.

The Solution: An Integrated 500 kW / 1 MWh Off-Grid Microgrid

Enerlution provided a containerized battery energy storage system with a rated power of 500 kW and an energy capacity of 1 MWh.

The system works together with:

  • 360 Rooftop Solar Panels: Generating renewable electricity to support daytime consumption.

  • 500 kW / 1 MWh Battery Energy Storage System: Storing surplus solar energy and providing additional power during periods of high demandTogether, these components form an autonomous off-grid microgrid, coordinating multiple energy sources to support the resort's electricity requirements.500 kW / 1 MWh BESS Project in Kyiv, Ukraine | Enerlution 2

How the Integrated Energy System Works

The microgrid combines three energy sources to support different operating conditions.

1. Solar Energy for Daytime Consumption

During daylight hours, solar power is prioritized to supply the resort's electricity demand. Surplus solar energy can be stored in the battery system for later use.

2. Battery Storage for Peak Power Support

When electricity demand increases, particularly during busy catering periods, the battery energy storage system can provide additional power to support peak loads3. Diesel Generation for Supplementary Power

The two diesel generators work alongside solar and battery storage, providing additional power when required.

This integrated configuration allows the energy sources to work together according to the resort's electricity demand and available solar generation.

Project Implementation and Technical Support

Beyond equipment supply, Enerlution participated in the project's implementation process.

The project followed several key milestones:

  • July: Equipment shipment.

  • Late September: On-site installation commenced.

  • Late October: System commissioning and handover completed.

Enerlution's team participated in installation, system commissioning and project handover, providing technical support throughout the implementation process.

Local technical support is also an important part of Enerlution's project service approach, helping address on-site requirements and support project implementation.

500 kW / 1 MWh BESS Project in Kyiv, Ukraine | Enerlution 3

Delivering Practical Energy Storage Solutions in Ukraine

This 500 kW / 1 MWh project demonstrates how battery energy storage can be integrated with solar PV and diesel generation to support an independent microgrid.

For off-grid commercial and industrial applications, an integrated energy system needs more than battery capacity alone. It requires appropriate system integration, coordination between different energy sources and practical project implementation experience.

Through this project in Kyiv, Enerlution continues to build practical experience in battery energy storage system integration and off-grid microgrid applications.

Looking for an Energy Storage Partner for Your Next Project in Ukraine?

Whether you are developing a commercial and industrial BESS project, a solar-plus-storage system or an off-grid microgrid, Enerlution is ready to discuss your project requirements.

Contact our team to explore energy storage solutions for your next project.

Enerlution – Energy Storage Solutions & Project Delivery.

prev
Energy Storage Systems: Types, Benefits, Applications and How to Choose
recommended for you
Get in touch with us

We are confident to say that our customization service is outstanding. Here is one of the testimonies from our old customer, They are highly capable of creating things to our exact requirements.

If you have any question,please contact us.

Email: Susan@enerlution.com.cn

Add: No. 33, Qiuju Road, Baiyan Science and Technology Park, High-tech Zone, Hefei, China


Privacy Policy

Copyright © 2026 Enerlution Energy Technology Co., Ltd. - https://www.enerlution.com.cn/ All Rights Reserved. | Sitemap
Customer service